Business Management, Search Engines, Theory & Models, Fashion & Trends, Industry News
Business & Industry Knowledge Portal
Tag It !! :
Menu
Home
Management Theory
Analysis
Articles
Brand Directory
Directory
Dictionary
News
Events
Coffee Painting
Jobs
Videos
News
Article Search
Book Search
Real Estate
Podcasts
Directory Search
Bookmark Search
Suggest Link
Search Engines
Articles Search
Bookmarking Search
Books Search
Directory Search
Job Search
News Search
Podcast Search
Real Estate Search
Video Search
Dictionary
Search Books On This Topic
Click Image To Buy " A Guide to the Project Management Body of Knowledge, Third Edition (PMBOK Guides)" From Amazon Now!! At Price : $49.95 Click Image To Buy " Agile Project Management with Scrum (Microsoft Professional)" From Amazon Now!! At Price : $39.99 Click Image To Buy " Head First PMP: A Brain-Friendly Guide to Passing the Project Management Professional Exam (Head First)" From Amazon Now!! At Price : $49.99 Click Image To Buy " The Fast Forward MBA in Project Management (Portable Mba Series)" From Amazon Now!! At Price : $21.95 Click Image To Buy " SharePoint for Project Management: How to Create a Project Management Information System (PMIS) with SharePoint" From Amazon Now!! At Price : $44.99
ยจ EXPLORE BOOKS ON THIS TOPIC   SEARCH AMAZON!!
 
Glossary & Dictionary

Project Management  Dictionary

 A B C D E F G H I J K L M N O P Q R S T U V W X Y Z 
Keyword  
Lag
Lag is the time delay between the start or finish of an activity and the start or finish of its successor(s). See FINISH-TO-FINISH LAG, FINISH-TO-START LAG, and START-TO-START LAG.
Late Finish
Late Finish dates are defined as the latest dates by which an activity can finish to avoid causing delays in the project. Many PM software packages calculate late dates with a backward pass from the end of the project to the beginning. This is done by selecting ANALYZE & PROCESS REPORTS from the Report pull-down menu.
Late Start
The latest time a task can start before it causes a delay in the project end date.
Late Start
Late Start dates are defined as the latest dates by which an activity can start to avoid causing delays in the project. Many PM software packages calculate late dates with a backward pass from the end of the project to the beginning.
Leveling
See Resource Leveling.
Link
A relationship between two or more tasks. See Logical Relationship.
Logical Relationship
A dependency relationship between two or more tasks or between tasks and milestones, such that one cannot start or finish before another has started or finished.